Governor Soludo lambasts and terminates the contract of NBHH Engineering Company over negligence and delay in delivering nine roads totaling 14.053 km in Okpoko.
The Governor announced the immediate termination of the road project contract when he visited the site unannounced on Tuesday, February 20, 2024.
The nine (9) road project in Okpoko include:
-Obodoukwu – Owerri Road (L= 2.884km W=12m)
-Ogbuagu-Ik Onuora-Anumudu-Mgbuka Amazu -Owerri Road (L= 2.992km W=7.3m)
-Edeh Road-School Road-Awalite- Ojoto -Owerri Road (L= 1.48km W= 9m)
School Road-Umuobom Street- Ojoto Street Junction (L= 0.576km W= 6m)
-Umuobom ST (Ojoto St Junction)- Adazi Ani ST – Owerri Road (L=1. 345km W=6m).
-Umenweke ST (Obodoukwu Junction) – Umeojiakor ST (School Rd Junction) (L=0.593km W=6km)
-Awalite (Ojoto Junction) – Anumudu (Mgbuka Amazu Junction) (L= 0.991km W= 6m)
-Uzii Street – Mission Street (Awalite Junction) (L= 0.538km W= 6m)
-Anumudu Street (Ik Onuora Junction) – Gmo Road (L= 0.350km W= 9m)}
14.053km.